Installation Process for Solar Panels

How do I schedule my solar installation?

A member of our Scheduling team will contact you once we have all the necessary approvals to move forward with the installation of your solar system.

How long will my installation take?

Most residential installations are completed within one day. Larger or more complex systems can take two or more days.

How long will my power be out?

Solar-only installations typically require the power to be out for 1-3 hours. Installations involving a Powerwall usually require the power to be shut off for 6-8 hours.

Do I need to be home for my solar installation?

This is dependent on the location of your electrical equipment. If anything is inside or any equipment will be installed inside, then we will need someone 18 years or older home for the duration of the installation.